Triangle Housing Association
Client : Triangle Housing Association
Value : £225,000.00
Duration : 60 weeks
Completion Date : January 2014
Consultant : ISD
KMDL Project Manager : D Lynn
Description of Work : New High Quality office Accommodation for Triangle Housing Association. Refurbishment of Existing Listed Stone Barn Building.
The Electrical services involved the following systems:-
* Mains & Sub Power Distribution
* Data Cabling Installation
* General & Emergency Lighting
* Mechanical Services Wiring
* External Lighting Installation
* TV Installation
* General Purpose Power
* Door Access System Installation
* Fire Alarm Installation
* Disabled Refuge Installation
* Intruder Alarm/CCTV Installation
* Lightning Protection Installation
* Public Address System
* Sound System Installation
* Disabled Toilet Alarm System
* Lift Installation
* Panic/Distress Alarm System
* Air Conditioning System
* Deaf Loop System
Email us: office@kmdlengineering.com